For hydropower investors in Georgia, securing land rights is far more than a property transaction. It requires navigating overlapping legal regimes governing state-owned property, superficies, forests, protected areas, subsoil and water resources. A coherent approach to these interconnected requirements is essential to reducing legal uncertainty, protecting investments and ensuring the long-term viability of HPP projects.
November 11, 2026
Levan Kokaia
Photo courtesy of Levan Kokaia, Legal Counsel, Georgian Renewable Energy Development Association (GREDA).

By Levan Kokaia
Legal Counsel, Georgian Renewable Energy Development Association (GREDA)

Introduction

The development of hydropower projects involves a complex combination of property rights, administrative authorizations and natural-resource regulations. While the availability of sufficient water resources and favorable hydrological conditions is essential for identifying a suitable location, the legal ability to use the relevant land is equally important for the successful implementation of an investment project.

This challenge becomes particularly significant where an HPP is planned on state-owned land. Unlike conventional commercial developments, hydropower projects frequently require access to several categories of land and natural resources simultaneously. These may include riverbanks, riverbeds, forest territories, underground areas, access roads, transmission corridors and land required for auxiliary infrastructure.

The legal status of these areas may differ substantially. Some may constitute ordinary state-owned immovable property, while others may be subject to special forestry, protected-area, water-resource or subsoil regimes. Consequently, obtaining a general right to use state property does not necessarily mean that all legal requirements for constructing and operating an HPP have been satisfied.

Georgia has established several legal mechanisms that may facilitate the use of state-owned land for private infrastructure development. The Law of Georgia on State Property regulates the transfer of state property for use, while the Civil Code provides for the right of superficies, allowing a person to construct and own buildings and structures on land belonging to another person. In addition, forestry, protected-area, subsoil, water-management, environmental and spatial-planning legislation establishes specific requirements that may apply to individual components of an HPP project.

The principal challenge is therefore not simply obtaining a land-use agreement. It is determining how these different legal regimes interact and how an investor can secure a coherent, enforceable and sufficiently long-term package of rights covering the entire project.

This article examines the relevant Georgian legislation from an investor-oriented legal perspective, with particular attention to state-owned land and the right of superficies. It also considers selected approaches in Germany and Austria, two European jurisdictions with substantial experience in hydropower development and the management of publicly owned water-related land.

The central argument is that Georgia could improve the predictability of HPP development by introducing a more coordinated mechanism for securing land rights, without weakening public ownership, environmental safeguards or the regulatory control of natural resources.

The Land Puzzle: Understanding the Different Rights Required for an HPP

The first step in determining the appropriate legal structure is to recognize that an HPP is not necessarily constructed on a single land plot.

Depending on its technical design, a project may require several geographically distinct areas for:

  • the powerhouse and associated permanent structures;
  • water-intake facilities and dams;
  • diversion channels and pressure pipelines;
  • underground tunnels and other technical installations;
  • construction and maintenance access roads;
  • transmission lines and substations; and
  • temporary construction areas and auxiliary facilities.

Each component may be subject to a different property and regulatory regime.

For example, the powerhouse may be located on ordinary state-owned land, while the water intake may occupy a riverbank or riverbed, the pressure pipeline may cross a state forest and the access road may pass through land administered by a different public authority.

The legal structure must therefore distinguish between several types of rights.

  • Ownership may be appropriate where the relevant land is legally capable of privatisation and acquisition is commercially justified.
  • Superficies may be appropriate for permanent buildings and structures constructed on or beneath land owned by the State or another person.
  • Lease or contractual use rights may be suitable for temporary construction areas, storage facilities and other land requirements.
  • Easements may provide the necessary legal basis for access roads, pipelines, transmission lines and other infrastructure crossing land belonging to third parties.
  • Special sectoral rights may be required for forest use, water-resource utilization or activities involving state-owned subsoil.

These instruments are not interchangeable. An agreement granting access to land does not automatically authorize the use of water resources, and an environmental decision does not independently establish a property right.

A bankable HPP project therefore requires the coordinated acquisition of all property rights and public-law authorizations necessary for construction and operation.

State-Owned Land: The Legal Framework for Obtaining Rights

The Law of Georgia on State Property

The Law of Georgia on State Property establishes the general legal framework for the administration, privatization and transfer of state-owned property.

A fundamental distinction must be made between acquiring ownership and obtaining the right to use state property.

For many hydropower projects, the latter is more appropriate. The investor may need long-term access to land and the right to construct permanent infrastructure, but does not necessarily need to become the owner of the underlying land.

Article 4 identifies categories of state property excluded from privatization. These include certain natural resources and categories of land and protected territories.

However, the exclusion of an asset from privatization should not automatically be interpreted as a prohibition on every form of economic use. The possibility of granting a right to use the relevant asset must be assessed separately under the applicable state-property and sectoral legislation.

This distinction is particularly important where an HPP requires the use of riverbanks, forest territories or other publicly owned land.

The investor must determine whether the relevant asset can be transferred for use, whether special legislation applies and whether additional administrative consent is required.

Transfer of State Property for Use

Article 36 provides the principal legal framework for transferring state property to private individuals and legal entities for use.

As a general rule, state property is transferred for consideration through an auction, with the consent of the property administrator, in one of the forms of use recognized by the Civil Code.

The applicable procedure and the competent property administrator must therefore be identified before an investor selects the appropriate contractual structure.

The Law also recognizes specific circumstances in which property may be transferred without an auction, subject to statutory conditions and the relevant decision-making procedure.

An investor should not assume that the strategic importance of renewable energy automatically creates an entitlement to obtain state land through direct transfer. The relevant statutory exception must be identified and its requirements satisfied.

This is particularly relevant for large HPP projects, where the investor may require access to several plots for extended periods.

The duration, permitted use and contractual conditions of the transfer must be compatible with the expected construction and operational periods.

Identifying the Property Administrator

The identification of the competent property administrator is another essential step.

Depending on the legal status of the land, the relevant authority may be the National Agency of State Property, a state institution, a forest-management body or another public entity acting within its statutory competence.

The investor should establish:

  • whether the land is registered as state property;
  • which authority administers it;
  • whether it is subject to existing third-party rights;
  • whether it falls within a forest or protected-area boundary;
  • whether it constitutes riverbed or other water-related property; and
  • whether the intended use is compatible with applicable statutory restrictions.

The registration of state ownership alone does not resolve these questions. A plot may be registered as state property while simultaneously being subject to a special statutory regime restricting its use.

Accordingly, cadastral due diligence must be accompanied by a substantive assessment of the property’s administrative and environmental status.

Superficies: The Most Relevant Property-Law Instrument for Permanent HPP Infrastructure

The Concept and Legal Characteristics of Superficies

The right of superficies, regulated by Articles 233–239 of the Civil Code of Georgia, is one of the most relevant legal instruments for constructing permanent infrastructure on land belonging to another person, including the State.

Under Article 233, a land plot may be transferred to another person for a specified period, granting that person an inheritable and transferable right to construct a building or other structure on or beneath the land.

The right may also extend to additional land that is not strictly necessary for construction but is required for the more effective use of the structure.

The maximum statutory duration of superficies is 99 years.

This mechanism is particularly suitable for hydropower development because the underlying land does not necessarily have to be transferred into the ownership of the project company.

For example, an investor may obtain superficies over state-owned land required for the powerhouse, permanent technical buildings or underground infrastructure, while the State retains ownership of the underlying land.

Ownership of Structures Constructed Under Superficies

One of the most important legal characteristics of superficies is established by Article 234.

A structure erected under a valid superficies right is treated as an essential component of that right and is registered as the property of the superficiary.

This arrangement creates a legal separation between ownership of the land and ownership of the infrastructure constructed on it.

From an investment perspective, this is a significant advantage. The investor may own the HPP structures without acquiring ownership of the underlying state-owned land.

However, the consequences of termination must be carefully examined.

Upon termination of superficies, the structure becomes an essential component of the land plot. Article 239 establishes the statutory consequences and compensation arrangements, subject to the parties’ contractual provisions and the applicable legal requirements.

This makes the contractual treatment of expiry, early termination, compensation and possible extension particularly important.

Transferability, Registration and Investment Protection

Article 235 addresses the transferability of superficies. Where the parties require the landowner’s consent for the transfer or lease of the right, that consent may be withheld only where significant grounds exist.

This is relevant to HPP investors because a project may be transferred, restructured or refinanced during its operational life.

Article 237 establishes the registration requirements for superficies and its priority as a real right over the relevant land plot.

Registration is therefore a fundamental component of the legal security of the investment.

An appropriately structured superficies agreement should address:

  • the exact cadastral boundaries of the land;
  • the permitted construction and operational activities;
  • ownership of permanent structures;
  • the duration and possible extension of the right;
  • the superficies fee and its adjustment;
  • transferability and lender protections;
  • access, maintenance and repair rights;
  • the treatment of infrastructure upon termination; and
  • compensation and early-termination arrangements.

Superficies over State-Owned Land: The Interaction of Public and Private Law

The application of superficies to state-owned land requires particular attention to the relationship between the Civil Code and the Law on State Property.

The Civil Code determines the nature and legal consequences of superficies. It does not, however, independently authorize a public authority to transfer state property outside the procedures prescribed by the Law on State Property.

Consequently, two separate legal requirements must be satisfied.

First, the competent authority must lawfully authorize the transfer of the relevant state property for use, following the applicable procedure.

Second, the superficies agreement must be validly concluded and the right registered in the Public Registry.

These two stages should be coordinated rather than treated as unrelated administrative and contractual matters.

For an HPP project, the public-law decision and the superficies agreement should identify the same land, permit uses and project facilities, while ensuring that the duration and termination arrangements are consistent.

The investor should also ensure that the agreement does not create uncertainty regarding the construction, ownership, maintenance or transfer of the relevant infrastructure.

Forest Legislation: Special Forest Use for Hydropower Infrastructure

Forest territories may be required for water-intake facilities, pipelines, access roads, transmission infrastructure and other HPP-related installations.

The Forest Code of Georgia provides a specific legal mechanism for these activities.

Article 68 expressly recognizes the construction, dismantling and operation of hydroelectric installations and associated infrastructure as purposes of special forest use. It also covers pipelines, roads, power-transmission communications, power grids and channels, as well as the design and engineering-geological works required for these purposes.

This is an important legislative basis for hydropower development in forest territories.

Nevertheless, the existence of this provision should not be interpreted as an unconditional right to construct an HPP in any forest.

The applicable forest category, protection regime and statutory restrictions must be examined.

The Forest Code distinguishes between different forest categories and establishes different conditions for the activities permitted within them.

In addition, the granting of a special forest-use right requires compliance with the relevant administrative procedure and applicable forest-use regulations.

An investor must therefore distinguish between the right to use state-owned land; the special forest-use right; the right of superficies for permanent structures; access and infrastructure rights; and applicable compensation and restoration obligations.

These rights may operate simultaneously, but none should be presumed to replace the others.

A particularly important practical issue is ensuring that the forest-use right corresponds to the actual technical design and geographical boundaries of the HPP. If the project design changes and additional forest areas become necessary, further administrative approvals may be required.

The legal assessment should therefore be undertaken before finalizing the project’s land requirements.

Protected Areas: Determining Whether the Project Location Is Legally Available

Protected-area legislation establishes a separate regime that may substantially affect the feasibility of an HPP project.

The Law of Georgia on the System of Protected Areas recognizes different categories of protected territories, including state reserves, national parks, natural monuments, managed reserves, protected landscapes and multiple-use areas.

The legal consequences of locating an HPP within or adjacent to such territories depend on the particular category, functional zoning and applicable management plan.

A strict nature reserve, for example, is subject to a significantly more restrictive protection regime than a multiple-use area.

Article 20 establishes that activities within protected areas are regulated according to the applicable category and individual management arrangements. Construction, commercial activities and the use of natural resources may be prohibited or restricted.

The distinction between protected landscapes and multiple-use areas is particularly relevant because these categories may accommodate certain forms of economic activity, but only within the limits established by their respective protection regimes.

The investor should therefore conduct a protected-area compatibility assessment before committing substantial resources to a project.

The assessment should identify:

  • whether the project area falls within a protected territory;
  • the relevant protected-area category and functional zone;
  • the applicable management plan;
  • whether construction and operation of the proposed infrastructure are legally permissible; and
  • whether biodiversity, habitat and other environmental restrictions affect the project.

Obtaining a property right cannot override restrictions imposed by protected-area legislation. Equally, an environmental authorization does not automatically establish a right to occupy or construct infrastructure on the relevant land.

In certain circumstances, relocating individual project components may be more commercially efficient than pursuing a land-use arrangement that is incompatible with the underlying protection regime.

Subsoil Legislation: Land Ownership Does Not Include Ownership of the Subsoil

Hydropower projects frequently involve underground construction, geological investigations, excavation and tunnelling.

These activities require an assessment of the Law of Georgia on Subsoil.

Article 2 establishes that the subsoil of Georgia is state property and that ownership of the surface land does not confer ownership of the subsoil.

This principle is particularly important for HPP development because an investor may obtain a property right over the surface while still requiring separate legal consideration of underground activities.

Article 6 identifies several forms of subsoil use, including geological study, mineral extraction and the construction and operation of certain underground structures.

However, not every underground construction activity should automatically be treated as commercial mineral extraction.

The legal classification depends on the actual nature and purpose of the activity.

An investor should distinguish between:

  • underground construction necessary for the HPP;
  • geological and geophysical investigations;
  • activities involving the extraction of mineral resources; and
  • other activities that constitute subsoil use under the Law.

Where the activity falls within a category requiring a license or registration, the applicable procedure must be followed.

This distinction is essential for projects involving underground powerhouses, tunnels and other facilities extending beneath state-owned land.

The superficies agreement should expressly cover the construction and operation of the relevant underground structures, while any separate subsoil requirements should be addressed independently.

Water Resources Management: A Separate Right from Land Use

Land-use rights and water-use rights must be treated as separate legal matters.

The right to use a riverbank or construct a water-intake facility does not, by itself, establish the right to use the water resource for electricity generation.

The Law of Georgia on Water Resources Management establishes the legal framework for the protection and sustainable use of water resources and introduces an integrated approach to water-resource management.

For HPP investors, the relevant issues include the legal basis for water use, environmental requirements, ecological flow, water quality and the applicable administrative procedures.

An important consideration is the phased implementation of the Law. As of November 2026, its application must be assessed in light of the provisions already in force, the amendments adopted during 2026 and the relevant transitional arrangements.

This is particularly important for HPP projects, whose development periods may extend over several years.

The investor should identify the regulatory regime applicable to the particular activity and the date on which the relevant application or operation is expected to take place.

The project documentation should also anticipate the possibility that additional water-use authorisations or compliance requirements may become applicable during construction or operation.

The legal distinction is fundamental:

  • a land-use right provides the legal basis for occupying and using the relevant land;
  • a water-use authorization provides the legal basis for the relevant use of the water resource; and
  • an environmental decision establishes the environmental conditions under which the project may proceed.

These three dimensions must be coordinated but should never be treated as substitutes for one another.

Other Relevant Legislation: Registration, Spatial Planning and Environmental Assessment

Public Registry and Cadastral Identification

The Law of Georgia on Public Registry and the applicable land-registration framework are essential for establishing the legal identity of the project area.

An HPP may involve multiple land plots, underground structures, access roads and transmission corridors.

The investor should ensure that the cadastral boundaries correspond to the actual technical requirements of the project.

The due-diligence process should identify existing ownership rights, registered encumbrances, third-party rights and discrepancies between cadastral information and the actual use or status of the land.

Where only part of a larger state-owned plot is required, the possibility of cadastral subdivision should also be assessed.

The registration of the relevant rights should be treated as a central element of investment protection, rather than a final administrative formality.

Spatial Planning and Construction Requirements

The Code of Georgia on Spatial Planning, Architectural and Construction Activities establishes the legal framework for spatial planning and construction.

Obtaining a property right does not automatically establish the right to construct a particular HPP facility.

The proposed use must also be compatible with applicable spatial-planning requirements, land-use conditions and construction procedures.

The investor should therefore assess construction feasibility alongside the land-rights analysis.

Environmental Assessment Code

The Environmental Assessment Code is another fundamental component of the legal framework.

Hydropower projects may be subject to environmental impact assessment or screening, depending on their capacity and the applicable statutory thresholds.

Environmental assessment may influence the project’s location, technical configuration, access roads, construction areas and the amount of land required.

For this reason, environmental assessment should not be treated as an isolated approval process.

Its findings should be integrated into the land-rights strategy to ensure that the rights obtained correspond to the project configuration that can lawfully be implemented.

European Experience: Practical Models from Germany and Austria

The experience of Germany and Austria is relevant to Georgia because both jurisdictions have developed sophisticated legal mechanisms for balancing public ownership, private infrastructure investment and the protection of water resources.

Their approaches are not identical to Georgia’s institutional system. Nevertheless, they provide useful examples of how land rights and water-use authorizations can be distinguished and coordinated.

Germany: Coordinating Hydropower and Water-Law Approvals

Germany’s Federal Water Act (Wasserhaushaltsgesetz – WHG) establishes the principal framework for the use and protection of water resources.

Under Sections 8 and 9, the use of water resources beyond ordinary public use, including hydropower-related abstraction, diversion and impoundment, generally requires a water-law permit or authorization.

Section 11a establishes specific procedural provisions for certain renewable-energy projects, including the construction, operation and modernization of hydropower installations, excluding pumped-storage plants.

This is an important example of legislative recognition that renewable-energy projects require procedures adapted to their specific development requirements.

The German approach demonstrates the value of coordinating water-law authorizations and related administrative procedures rather than treating every approval as an entirely separate process.

Lesson for Georgia: A coordinated HPP approval mechanism could allow the competent authorities to assess land requirements, water-use arrangements, environmental obligations and construction-related applications in a structured and mutually consistent manner.

Austria: The Public Water Estate and Infrastructure Rights

Austria offers a particularly relevant model through its Water Rights Act 1959 (Wasserrechtsgesetz 1959).

Section 4 regulates the Public Water Estate (Öffentliches Wassergut), which includes certain publicly owned riverbeds and flood-discharge areas.

These properties serve important public purposes, including the protection of ecological functions, flood management, groundwater protection and the construction and maintenance of water-related infrastructure.

Importantly, Section 4(8) restricts the granting of other real rights over such property unless the competent authority has established that the proposed right will not impair the statutory purposes of the Public Water Estate.

Section 9 separately requires water-law authorization for uses of public waters beyond ordinary public use and for the construction or modification of facilities serving such use.

This creates a clear distinction between the legal right to use the land and the authorization to use the water resource.

Lesson for Georgia: A dedicated framework for state-owned riverbanks and other water-related land could provide investors with clearer procedures for identifying the relevant property administrator, obtaining contractual use rights and coordinating those rights with water-use authorizations.

Comparative Significance

The German and Austrian approaches demonstrate two complementary principles.

Germany illustrates the importance of coordinated administrative procedures for hydropower-related water use.

Austria demonstrates the value of a clearly defined legal regime for publicly owned water-related land.

For Georgia, combining these principles could reduce procedural uncertainty without compromising public ownership or environmental protection.

A Practical Legal Roadmap: How Investors Can Unlock the Land Puzzle

Based on the Georgian legal framework and the comparative experience of Germany and Austria, investors should approach land acquisition and use through a structured legal process.

Stage 1 – Preliminary land due diligence: Identify every land plot required for the project and establish its cadastral boundaries, ownership, registered encumbrances and administrative status.

Stage 2 – Classification of property and natural-resource regimes: Determine whether each plot is ordinary state property, forest land, protected-area territory, riverbank or riverbed land, municipal property or privately owned land.

Stage 3 – Selection of the appropriate legal instrument: Determine whether the project requires ownership, superficies, lease, easement, special forest-use rights or a combination of these mechanisms.

Stage 4 – Identification of competent authorities: Identify the relevant state-property administrator, forest-management body, water-management authority, environmental authority and other institutions with statutory competence.

Stage 5 – Environmental and sectoral assessment: Establish whether the proposed project is compatible with forestry, protected-area, subsoil, water-resource and environmental requirements.

Stage 6 – Contractual and investment structuring: Ensure that the agreements provide sufficient legal certainty for construction, operation, maintenance, financing, refinancing and potential transfer of the project.

Stage 7 – Registration and completion: Register the relevant property rights and obtain all sector-specific administrative rights and authorizations before commencing the activities for which they are required.

The Land Rights Matrix

One particularly useful instrument would be a consolidated Land Rights Matrix.

This document should identify every land plot, its legal status, the applicable legislation, the competent authority, the required property right and the status of the relevant administrative procedure.

Project componentPotential legal instrumentAdditional legal assessment
PowerhouseSuperficiesState-property transfer and construction requirements
Water intakeProperty-use right / superficiesWater-use authorisation
Pressure pipelineEasement / superficiesForest and land-use restrictions
Access roadEasement / land-use agreementForest and construction requirements
Underground tunnelSuperficiesSubsoil legislation, where applicable
Transmission corridorEasementLand registration and sectoral requirements
Temporary construction areaLease / contractual useLand-use and environmental conditions

The matrix should form part of the project’s legal due diligence and development documentation.

It would also enable the investor to identify potential legal obstacles before significant engineering and financial resources are committed.

Conclusion

Securing land rights for hydropower projects in Georgia requires more than obtaining permission to use a particular state-owned plot.

The legal structure of an HPP project must accommodate several interconnected but legally distinct matters: ownership and use of land, construction of permanent infrastructure, access to forest territories, restrictions applicable to protected areas, underground construction, use of subsoil and the utilization of water resources.

The Law of Georgia on State Property provides the principal framework for transferring state-owned property for use. The Civil Code establishes the right of superficies, which allows investors to construct and own permanent structures on land belonging to another person for a period of up to 99 years. The Forest Code recognizes hydropower infrastructure as a permissible purpose of special forest use, subject to statutory restrictions. Protected-area, subsoil and water-resource legislation impose additional requirements that must be assessed independently.

The principal investment challenge is therefore not necessarily the absence of legal instruments. It is the fragmentation of the applicable procedures and the need to coordinate several public authorities and legal regimes within a single project.

Germany and Austria provide useful comparative lessons. The German approach demonstrates the value of coordinated administrative procedures for water use and hydropower development. Austria illustrates how publicly owned water-related land can be systematically identified and administered through a dedicated property-management framework.

For Georgia, the most effective solution would be to establish a more integrated and predictable mechanism for securing land rights for hydropower projects.

Such a mechanism could include standardized superficies agreements, clearer rules for infrastructure easements, a dedicated procedure for using state-owned riverbank land and coordinated administrative assessment of the relevant property and natural-resource rights.

The ultimate objective should be to allow an investor to establish, at the earliest stage of project development, not only whether a location is technically suitable for an HPP, but also whether all the land and natural-resource rights necessary for construction and operation can be secured on a legally sustainable and commercially bankable basis.

Unlocking the land puzzle is therefore not simply a matter of simplifying administrative procedures. It requires a coherent legal framework that reconciles public ownership, private investment and the sustainable use of natural resources.

A transparent and predictable land-rights framework would reduce development uncertainty, strengthen investor confidence and contribute to Georgia’s ability to attract long-term private investment into its hydropower sector.

Author’s note: This article is a legal analysis and should be checked against the consolidated legislation and implementing regulations in force on the intended publication date, particularly the transitional provisions of Georgia’s Law on Water Resources Management and the applicable forestry and protected-area rules.

Contributor note: This article was contributed by Levan Kokaia, Legal Counsel of the Georgian Renewable Energy Development Association (GREDA). The legal analysis and interpretations expressed in the article are the author’s own.

Latest Headlines

Stay informed

News, projects and analysis from Georgia’s renewable energy sector.

No spam. Unsubscribe anytime.

Related Articles