GECO has applied to the European Commission for Project of Mutual Interest status for the Caspian–Black Sea–Europe Green Energy Corridor, opening a formal EU assessment process for the planned Azerbaijan–Georgia–Romania–Hungary link.
Renewable Georgian Energy says Goldwind will supply, install and commission turbines for the Pirveli and Chero wind farms, which are targeting commercial operation by the end of 2027.
The four governments have signed a strategic partnership agreement at COP31 in Antalya, setting out cooperation on a planned 2–3 GW overland electricity corridor via Türkiye and Bulgaria.
Georgian State Electrosystem says it has discussed the proposed Imereti 1 wind project with developer Infinite Energy LLC, including a new 500 kV substation intended to transfer to GSE after construction.
The Georgian Energy Development Fund has installed solar micro-power plants for 58 families in 16 high-mountain villages, where connection to the central electricity grid was not considered feasible.
The proposed financing covers 40.6 MW of new solar capacity and refinancing for five operating plants, while negotiations on the loan agreement continue.
A 33.06 kWp rooftop solar installation at the Evangelical-Lutheran Church in Tbilisi has been operating for around three years. The church says the system now generates more electricity over the year than the site consumes, while the original project calculations indicated a payback period of around six years.
The developer says the planned wind farm will affect no more than 3% of the licensed forest area, while more than GEL 5.6 million is expected to be paid in compensation related to tree removal.
Installation of all 33 turbines has been completed at the Ruisi Wind Power Project in Shida Kartli, as the 206 MW facility moves toward grid connection and commissioning.
A proposed modification to the Kaspi wind project would increase its installed capacity by 26 MW and fully double-circuit the associated 110 kV transmission line.
The industrial self-consumption project in Rustavi will combine on-site solar generation with zero-export control and provision for future battery storage.
The Green Energy Corridor has completed its feasibility study and is moving toward implementation as participating countries develop a regional electricity-trading framework.
Procurement delays have affected Georgia’s first grid-scale battery project, which is intended to strengthen system flexibility and support greater renewable-energy integration.
The Black Sea submarine cable has gained EU Project of Mutual Interest status as Georgia and its regional partners advance technical and institutional preparations.