GECO Reaffirms 2032–2040 Phasing for Black Sea Green Energy Corridor

The first planned 1.3 GW link would run through Georgia to Romania in 2032, followed by two further links by 2040.
November 23, 2026
Photo: Aspen Institute Romania

Green Energy Corridor Power Company (GECO) has restated the planned 2032 start date for the first electricity link in the Caspian–Black Sea–Europe Green Energy Corridor.

At the Bucharest Forum on 19 November, GECO General Manager Yusif Gayibov spoke about the financing, cross-border regulation, supply-chain capacity and subsea-security issues that will shape the project’s next phase.

The corridor is planned as three separate ±525 kV HVDC links, each with a nominal transfer capacity of 1.3 GW:

  • 2032: Link 1 — total corridor capacity of 1.3 GW
  • 2036: Link 2 — total capacity of 2.6 GW
  • 2040: Link 3 — total capacity of 3.9 GW

These are planning dates recorded in ENTSO-E’s Ten-Year Network Development Plan 2026, rather than confirmed commissioning commitments. GECO says the schedule will be confirmed through its roadmap to a final investment decision.

Georgia is central to all three routes. The first link is planned to run from Baku through Ksani and Anaklia to Constanța Sud in Romania, with an onward extension towards Albertirsa in Hungary. The second and third links would use the Tskaltubo converter station and the Georgian coast at Poti.

The first link’s onward Constanța Sud–Albertirsa section is designed for 2 GW, compared with the 1.3 GW capacity of the HVDC link itself.

GECO’s October investment presentation put total investment in the corridor and associated renewable generation at around €22.1 billion: €14.3 billion for transmission infrastructure and €7.8 billion for dedicated renewable generation capacity.

The presentation cited CESI projections that renewable-electricity exports to the EU could reach 8 TWh a year after the first link enters operation, rising to 20 TWh annually by 2040. It also projected annual economic benefits of €860 million after Link 1, €1.8 billion after Link 2 and more than €3 billion after Link 3. These are feasibility-study projections, not committed outcomes.

The feasibility study was approved by the four participating governments in July. GECO says the project has since entered its development phase, including tender preparation and work on the roadmap to a final investment decision.

Sources: GECO project documentation; GECO Bucharest Forum statement, 19 November 2026; GECO October 2026 investment presentation, reported by Trend.az.